Modeling Main Pipeline Stations

It is necessary to specify correct boundary conditions while modeling main pipeline stations: valve station, pig launcher, pump and compressor station etc. Sometimes engineers use fixed anchor at the points of connection of main pipeline. This trick work for above ground piping, but doesn't work for buried main pipelines. The wrong model of pig launcher station is shown below.

For a very long buried pipeline the fixed anchor is not enough to achieve enough safety margin. Even if temperature difference between installation and operation temperature is very small 10-40 degrees, then temperature expansion can be up to 100 mm due to huge length. Such a big displacements can damage the piping inside the station.

To correctly model the temperature expansion model must include the part of main pipeline with a length greater than La. Where La is a sliding zone length, also called virtual anchor length. In sliding zone pipe moves along it's axis. But in restrained zone pipe doesn't move. The maximum displacement umax will be a constant for any length of pipeline greater than La.

 

To correctly model the temperature expansion of main pipeline, just add the pipe with length greater than La value (see picture below).

La value can be found by three ways:

To select the pipe length just add the pipe with some initial length. For example 100 m. Then run analysis and check stresses or support loads. Then increase the pipe length, for example to 150 m and run analysis again. If stresses or support loads become greater, then you need to increase the pipe length again and repeat analysis. Continue increasing of the pipe length until the stresses or support loads become almost the same as at previous analysis. It means that the pipe length already greater than La.

Calculation of virtual anchor length (sliding zone length) in Start-Elements looks like this:

Then the correct model is ready, maybe you will need to add U-, Z- or L-shape pipe loops to compensate the temperature expansion of connected main pipeline that is shown by dotted arrow on the picture below.

See also: Restrained and Unrestrained Zones of Buried Pipelines